We manufacture soundproofing materials at our own plant at Palwal in Haryana, India, and supply them into Diu. Diu is a small coastal tourism market where salt air and a fixed season decide almost everything.

SoundBlanket MLV
2100 kg per cubic metre. 2.5 mm STC 30 at 5.25 kg per sq m, 4 mm STC 34 at 8.4, 6 mm at 12.6
BassBloc
1800 x 900 x 20 mm, 100 kg per cubic metre, NRC 0.85
Principle
Mass, then decoupling, then cavity absorption, then sealing
Test standards
ASTM E90 for the barrier, ASTM C423 for the absorber
Lead time
4 to 7 working days for stock items
  • ASTM E90 for the barrier, ASTM C423 for the absorber
  • Made at our own plant, Palwal, Haryana, India
  • One batch across the order, no blending between runs

We are the manufacturer. There is no local office and we do not claim approvals we do not hold. What you get is factory pricing, one consistent batch across the order, and a straight answer on what the material will and will not do.

01 / The material

What you are buying, and what it fixes in Diu

The blocking side of the range taken together: mass loaded vinyl, resilient layers, cavity absorption and the build-ups they belong in. This is the page for someone whose problem is noise getting through, not a room that sounds wrong.

Work reaching us from Diu is mostly hotels and guest houses, restaurants and bars, heritage properties, offices, clinics.

RC frame housing and worker accommodation with hard floors, close to industrial estates.

  • Independent leaf A second wall that does not touch the first. Nothing else comes close for the money.
  • Resilient bar Where a full independent leaf will not fit. Effective, and very easy to short circuit with one wrong screw.
  • Floating floor Resilient layer and deck, to break impact energy before it reaches the structure.
  • What it will not do Soundproofing fails at the gaps, not the materials. A service penetration, a back to back socket, or a door undercut will undo a correctly built wall.

Full specification

Thickness, density, NRC by frequency, fire class, standard sizes and build-up detail for our soundproofing materials are on the main product page. This page covers what that means for a project in Diu.

SoundBlanket mass loaded vinyl BassBloc sound absorber Wall soundproofing systems

02 / Data sheet

Published specification, identical wherever we ship it

We publish one data sheet for every market. If a supplier quotes you a different figure for the same product in a different city, one of the two numbers is wrong.

  • Light retrofit2.5 mm membrane. Where depth is not available
  • Standard partition4 mm membrane on an independent leaf. The common specification
  • Heavy6 mm membrane and full decoupling. Plant, machine enclosure, low frequency
Soundproofing materials: published specification
SoundBlanket MLV2100 kg per cubic metre. 2.5 mm STC 30 at 5.25 kg per sq m, 4 mm STC 34 at 8.4, 6 mm at 12.6
BassBloc1800 x 900 x 20 mm, 100 kg per cubic metre, NRC 0.85
PrincipleMass, then decoupling, then cavity absorption, then sealing
Test standardsASTM E90 for the barrier, ASTM C423 for the absorber

Where a consultant is already engaged on a Diu project, we supply to their specification and send the test reports rather than describing them. More on working with acoustic consultants.

03 / In this market

What the buildings in Diu do to the specification

  • Salt air is relentless

    PET felt does not absorb moisture, rot or corrode. On an exposed coast that is the whole material selection argument.

  • Season dates are fixed

    Work has to finish before the season opens. Real dispatch and transit dates matter more than a marginally better price.

  • Heritage stone buildings

    Thick masonry with hard finishes that hold sound for a long time, and a structure that usually cannot be altered.

  • Sensible quantities

    A small market does not need a full container. We would rather quote a part load that works.

  • Plant and HVAC

    Dense industrial estates with compressors, presses and generator sets close to offices, canteens and housing.

  • The housing stock

    RC frame housing and worker accommodation with hard floors, close to industrial estates.

If you are specifying for a Diu project, we can give you a section, a BOQ and the honest limits of each layer. See how we support architects.

04 / Climate and durability

Durability in Diu, before acoustics is discussed

Diu is hot summers, mild winters and a distinct wet season, and that narrows the sensible material list before acoustics is even discussed.

PET felt handles the wet months without absorbing moisture or feeding mould. Timber and wood wool want a ventilated cavity and a stable indoor RH.

The risk we design against here is wet-season humidity behind linings.

Interior designers tend to arrive with the look already decided. We will tell you which finish gets there without losing the acoustics. See how we work with interior designers.

05 / Supply

Getting it to Diu, with real dates

Supply into Diu
Made atOur own plant, Palwal, Haryana
Reaches site inthree days
Dispatch2 to 4 working days
To sitethree days
PackingRolls on core tubes, boards palletised, fixings and tapes listed on the same packing list.
Lead time4 to 7 working days for stock items.

Standard items dispatch in 2 to 4 working days from our plant at Palwal. Grooved panels and custom colours take longer, and we say so before you order, not after.

By road from Palwal, roughly twelve hundred and fifty kilometres, normally three days on a dedicated truck.

06 / Read this first

Four honest warnings before you buy

  • The wrong product for the problem

    Soundproofing fails at the gaps, not the materials. A service penetration, a back to back socket, or a door undercut will undo a correctly built wall. We would rather spend the conversation on the detail than on the product.

  • Coverage bought instead of a target

    Lining every surface is a purchase, not a result. We would rather calculate the area against a reverberation target and sell you less of it.

  • Suppliers who imply a Diu presence

    Ask any supplier where the material is made and who carries the warranty. We make it at Palwal in Haryana and we say so on every page, including this one.

07 / In projects

In finished rooms

Acoustic curtains
Acoustic curtains
Acoustic fabric panels
Acoustic fabric panels
Custom soundproofing systems
Custom soundproofing systems
Acoustic wall panels in an airport lounge, soundproofing materials in Abu Dhabi
Acoustic wall panels in an airport lounge, soundproofing materials in Abu Dhabi
Auditorium with wooden acoustic wall and ceiling treatment
Auditorium with wooden acoustic wall and ceiling treatment
Cinema hall with fabric acoustic wall panels
Cinema hall with fabric acoustic wall panels
FAQ

Diu: questions we are actually asked

Are these soundproofing materials made in Diu?

No, and we will not say otherwise. We manufacture at our own plant at Palwal in Haryana, India, and supply into Diu as the manufacturer rather than through a dealer. Diu is a small coastal tourism market where salt air and a fixed season decide almost everything. You buy at factory prices with one consistent batch across the order.

What do you look at first on a Diu enquiry?

PET felt does not absorb moisture, rot or corrode. On an exposed coast that is the whole material selection argument. Work has to finish before the season opens. Real dispatch and transit dates matter more than a marginally better price. Those two things move the build-up far more than the panel figure does.

Is this the right material for Diu conditions?

Diu is hot summers, mild winters and a distinct wet season. PET felt handles the wet months without absorbing moisture or feeding mould. Timber and wood wool want a ventilated cavity and a stable indoor RH. The failure we design against here is wet-season humidity behind linings.

What is the delivery time into Diu?

made at: Our own plant, Palwal, Haryana, reaches site in: three days, dispatch: 2 to 4 working days. Standard items dispatch in 2 to 4 working days from our plant at Palwal. Grooved panels and custom colours take longer, and we say so before you order, not after.

What should you not buy soundproofing materials for?

Soundproofing fails at the gaps, not the materials. A service penetration, a back to back socket, or a door undercut will undo a correctly built wall. We would rather spend the conversation on the detail than on the product.

What is the minimum order and how is it packed?

Minimum order is confirmed with the quote. Rolls on core tubes, boards palletised, fixings and tapes listed on the same packing list.

Next step

Send a plan and a section, get a real build-up

A plan and a section is enough. We will come back with a build-up, a BOQ and a delivered date, and we will say so if what you are asking for will not work.